Date Expression Compare precondition
This is the JSU for Jira Cloud documentation. If you are using JSU on Jira Server or Data Center, see our JSU Server/Data Center documentation.
Description
The Date Expression Compare precondition compares the value of a date field with a date expression. For example, the date field must be more recent than the actual date.
Configuration
You must select the date field, the comparison condition, the date expression, and whether to include the time part for comparison.
Example
A workflow is configured so that the Resolve transition has the Date Expression Compare check where Due date > 1w 1d
. If the transition is executed, and the due date is more than a week and five days away, the time left at resolution will be set to > 1w
.