Burndown chart

Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 4 Next »

Burndown chart shows you how your team is progressing against the work for a release or an issue. You will be able to see if your release or issue is on track, ahead or behind.

👉 Read more about Release burndown charts in our blog article

Burndown 1 (screenshot)

How to access Burndown chart

  1. Go to Swanly via Apps > Swanly roadmaps

  2. Click on release or issue name to open it’s details

  3. Click Expand button in the top right corner of the screen

  4. Click on Burndown chart tab

Burndown 2 (screenshot)

To display the Burndown chart you will need to have the following:

  • set start and end date for your release (issue)

  • add issues in version (child issues)

👉 More on how to add issues to the release

On the vertical % In Progress axes chart shows you percentage of remaining work and gives you 3 options to track progress:

  • Issue count

  • Story points

  • Original time estimate

On horizontal Time axes, it shows dates and Release (Issue) end date is highlighted.

Burndown 3 (screenshot)

  • No labels