In the example below, a task can be in the OMEGA Box (own scope) + Program Increment 1 (sub-scope Box) + Iteration 2 (sub-scope Box)
...
Start/end date not specified
...
A newly created task changes based on other tasks, but it can also force other existing tasks to change.
New task | impacted Impacted by | impactsImpacts |
---|---|---|
dependencies | a task can be a target of a dependency (it is affected by the source task) | a task can be a source of a dependency (it affects other tasks) |
scheduling mode | "auto top-down" parent impacts:
| all tasks impact an "auto bottom-up" parent |
...
Position in the tree is vital, as it determines what task is in a the role of a 'parent' and 'child.' Tree relationships determine how the scheduling mode rules are executed.
...
"Epic link" is listed as a structure builder:
...
The task is created directly in Jira. "Epic link" field has been filled in:
...
other "auto top-down" tasks
"auto bottom-up" tasks
During task creation:
situationSituation | outcomeOutcome |
---|---|
New task fits within the parent task period | no changes made to the period of the new task |
New task partially fits within the parent task period | task duration shortened - days outside of the parent task period are 'cut off' |
New task has no overlap with the parent task period | task duration = 1d task placed on a timeline closer to the start/end dates specified during task creation |
...
"auto top-down" tasks
"auto bottom-up" tasks
During task creation:
situationSituation | outcomeOutcome |
---|---|
New task fits within the parent task period | no changes made to the period of the new task |
New task partially fits within the parent task period | task duration shortened - days outside of the parent task period are 'cut off' |
New task has no overlap with the parent task period | task duration = 1d task placed on a timeline closer to the start/end dates specified during task creation |
...
Task period alignment settings of a Box regulate the relationship between a task and a Box it's in.
task Task period alignment | resultsResults |
---|---|
no alignment | task period = unaffected |
precise alignment | Task period = Box period |
smart adjustment | Task's time frame aligns with the start and/or end date of a Box. Task's length remains unchanged (whenever possible) |
...