The following effort modes are available:

...

Contents:

Table of Contents
minLevel1
maxLevel6
outlinefalse
styledefault
typelist
printabletrue

About the effort modes

Effort modes in BigPicture determine the source of data used to calculate resource workload distribution. They let you estimate tasks and track the time your team members spend on them in three different ways:

...

...

Effort modes determine the source of data used for the calculation of workload distribution

The effort mode can be shown expressed in the following units:

  • Hours

  • Man-days

  • Percent

  • Story points

Note that not all units are available in every effort mode.

Effort mode

Unit

Hours

Man-days

Percent

Story points

...

Original Estimate

Yes

Yes

Yes

No

Remaining Estimate

Yes

Yes

Yes

No

Story Points

No

No

Yes

Yes

Access the effort modes and units

You can find the effort mode and unit from the dropdown menu under the button with the “speedometer” icon on it.

...