Introduction

Managing resource availability is vital for all your projects, as it affects all other project parameters. The availability factor can increase or reduce the team members' capacity in a specified period. 

Image Removed

Availability and Capacity

...

Availability and capacity

Add a team member

When you add a team member, specify the availability for that period. Image Removed

...

...

Add a

...

membership entry

When you add a membership entry (for a team member), specify the availability for that period. Image Removed

...

...

Edit a membership entry

Open the list of membership entries for a team member by clicking on their username:Image Removed

...

You can edit the availability value of a membership entry. Image Removed

...

Limitations: you can't edit the value if the team was inherited. Changes have to be made in the box the team was created in. 

You can set availability for each team member. Availability impacts the capacity.

...

Info

Individual capacity in the Resources module is calculated dynamically and changes depending on the Team Filter you use.

Expand
titleSee the example

For example, Albingo is assigned to the TeamiOS starting on the 7th of July for 50% of his time. Albingo is working full-time 8h/d as specified in the Workload Plan. 

His daily capacity is 8h*50% = 4h. The 4h capacity applies to both the individual and team, as Albingo is the only member of the iOS Team. Since there are no tasks assigned to Albingo, the Capacity on the 1st of June = Remaining capacity = 4h.

...

Image Added

In the team-centric view, on the 1st of June the Capacity = Remaining capacity = 4h, as there are no tasks assigned to Albingo.

...

Image Added