Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Table of Contents

Introduction

You can set baselines and track deviations from the initial schedule to assess the project's performance.

Create and delete baselines for all the tasks or selected tasks only. Baselines are displayed as bold lines under tasks. Baseline dates reflect the task position at the moment of adding a baseline.

...

...

Baseline

...

fields

...

Baseline fields in column views

The Baseline start date and Baseline end date are available as built-in fieldsstored in BigPicture. Field mapping is NOT available for baseline start/end date - this means that data is stored only in BigPicture and is NOT synchronized with any other platformmonday board columns.

Actions on baselines

Excerpt
namebaselines-task-dates

Baselines apply to tasks that have start/end dates. Baselines CANNOT be created for a task with only one date.

View baselines

To display baselines on the timeline:

...

Baseline dates reflect the task position at the moment of adding a baseline.

...

Show/hide baselines

  1. Go to the Gantt module.

  2. Click the View menu icon in the top-left corner.

  3. Check the Baselines option.

...

  1. (blue star)

  2. Select the Baselines option

...

Who can manage baselines?

A box admin can determine who can create, edit and delete baselines. Other users are still able to view baselines.

The permission to manage baselines can be granted to:

  • Box Admin and Box Editors (default)

  • Box Admins

Baseline permissions are edited in Box Configuration > Tasks > Baselines.

...

Actions

Create baselines for all tasks

To create baselines for all tasks shown in the issue list (WBS):

...

Excerpt
namebaselines-task-dates

A baseline CANNOT be created for a task without dates.

  1. Go to the Gantt module.

  2. Click the Data menu icon in the top-left corner. (blue star)

  3. Select the Baselines > Create option.

  4. Click Overwrite to confirm.

Delete baselines

...

of all tasks

To delete baselines for all tasks shown in the issue list (WBS):

  1. Navigate Go to the Gantt module.

  2. Click the Data menu icon in the top-left corner. (blue star)

  3. Select the Baselines > Delete option.

  4. Click Delete to confirm.

Create a baseline for a single task

To create a baseline for a single task:

  1. Navigate Go to the Gantt module.

  2. Right-click on the a task

    1. on

    the timeline.
    1. a timeline OR

    2. on the task list

  3. Select the Baseline > Create option.

...

Delete a baseline

...

of a single task

To delete a baseline for a single task:

  1. Navigate Go to the Gantt module.

  2. Right-click on the a task

    1. on

    the timeline.
    1. a timeline OR

    2. on the task list

  3. Select the Baseline > Delete option

...

Tasks without dates

Existing baselines are unaffected when the start/end date of a task is removed.

Baseline dates are based on the start/end dates of a task. You can’t create a baseline for a task without dates.

Limitations

  • You cannot create multiple baselines for a task.

  • You can’t create a baseline for a task without dates