Introduction

Capacity represents the number of hours a resource can contribute each day.

Capacity, in combination with task workload, makes it possible to monitor workload distribution and avoid over/under-allocation of resources.

Capacity modifiers

Capacity is based on a workload plan assigned to a resource.

Capacity is reduced by

Workload plan

Efficiency specified for a workload plan assignment

Holiday plan

Non-working days

Absence

  • entire day

  • half-day

Capacity = 0

Capacity is zero when

Workload plan

  • there is a non-working day in a workload plan (0-hour days)

  • all workload plans have been removed from a resource

Holiday plan

  • a holiday plan assigned to a users marks a day as non-working

Absence

  • an whole day absence has been added for a user

View resulting capacity

Workload plans cannot be viewed in box modules. This information is available only in BigPicture Administration.

The resulting capacity can be viewed in the Resources module.

...

If a resource is assigned to a team 100%, their individual capacity is synonymous with team capacity. So it's 100% (not 0h).

Individual capacity in portfolio boxes

Individual capacity in none scope boxes such as the root (Home) and portfolio boxes presents:

  • The user’s calendar capacity if the user is not assigned to any team.

  • The user’s calendar capacity if the sum of the user’s team capacities is greater than the user’s calendar capacity.

  • The sum of the user’s team capacities if the sum of the user’s team capacities is less or equal to the user’s calendar capacity.

Workload cell coloring is calculated based on the capacity selected above.

Expand
titleSee the example

Collin is assigned to 2 different teams simultaneously. His team capacity is 40 hours per week because his work limit is 40 hours (calendar capacity).

image-20240711-082858.pngImage Added

Team Capacity

The formula for calculating the capacity of a Team:

...

  • You need to be in the Individual view.

  • Capacity has to be selected in the View dropdown.

  • Aggregation of the Time period has to be set to Daily.

...

Capacity pop-up elements

element

description

date

Image Modified

Capacity is always checked for a particular day - date information is listed in the top right corner.

working day/
day off

Image Modified

Information about whether a resource is working on a given day

Resource name and avatar

Image Modified

Capacity

Image Modified

Factors and Details

Relevant elements that lead to a particular capacity are listed.

Image Modified

Capacity exceeds Workload Plan hours

...