There are different ways in which you can add tasks using the Gantt module. You can add tasks one by one or add a group of tasks to the scope of the Box. When you use the Gantt's interface, besides adding Jira issues, you can also add Basic tasks which will only be displayed using the App.Image Removed

...

Info

Task duration

If you do not specify the task duration while creating a new task, it will be set to 1 day.

By default, the App requires two points on the timeline (in other words two dates) to generate a taskbar and determine the start and endpoints. Those points in time are the task's "Start Date" and "End Date" and are stored as "Start Date" and "End Date" custom fields by default.

If a task with no start and/or end dates is added to the scope of a Box, the App will pick the "Original Estimate" value to calculate the duration and set the task's "Start Date" to the "Creation Date".

Following this logic, if no "Original Estimate" value is available, the App will again use the "Creation Date" as "Start Date", and when the "End Date" is empty, then it picks the resolution date (if the issue was resolved) instead. This usually means that a task will be set as a 1-day duration starting on the "Creation Date". With the "Original Estimate" mapped as the start or end dates, it will represent the duration of a taskFind out more about task dates on the Task dates page.

Box scheduling settings and scheduling mode of tasks can automatically overwrite start/end dates.

Creating new tasks

...

Jira tasks

Create a new Jira task (issue) using the task creation screen. Any issue type can be added as a task. If a task is already selected, the new task will be added just beneath it on the same level in the hierarchy.

Depending on the project synchronization settings, adding new tasks might update different fields mapped as start and end dates. To learn more go to the Fields configuration page.

For example: If the "Start Date" field is not synchronized or it is not added to the appropriate issues screen , when you add a task there will not be any update of the "Start Date" field. However, when the "Start Date" is synchronized, adding a task without setting the start date estimate will result in a task update, and the "Creation Date" will be used as the "Start Date" (the "Creation Date" will also be used as the "End Date" if the task is not resolved).

Warning

In the cloud version of the App, you cannot create a Jira sub-task on Gantt - this functionality works only for the Server version of the App.
More information on the differences between cloud and server versions of the App can be found here.

...

can be found on the Cloud vs. Data Center - Key Differences between Platforms page.

...

Tip

Make sure you have selected the correct Jira project. Otherwise, you might unintentionally create a task in the wrong place.Image Removed

If the App overwrites the manually specified start/end dates, make sure to verify Box scheduling settings and  verify box scheduling settings and task scheduling mode of tasks.

Expand

For example: if the parent task is in the "auto top-down" mode, the task period will be automatically altered during creation.Image Removed

Image Added

A new Jira task is created. Image Removed

Image Added

Start/End dates are set to 2023.Image Removed

Image Added

The task period has been automatically adjusted. Image Removed

Image Added

Basic tasks

Create a basic task and task and add it to the list of tasks. Such tasks will not be synchronized with your Jira or connected tools. For example, you will not see a basic task in your Jira project.Image Removed

...

Task templates 

This requires you to create a template first using the Task the Task Template Creation menu Creation menu in the Box configuration.Image Removed

...

Import from file

Import You can import your task templates from other tools like MS , such as MS Project, MS Excel, or a CSV file. For detailed instructions on how to import tasks more information, see the Import from a file, refer here page. Image Removed 

...

Clone existing scope

Use your existing Boxes as templates and clone the scope to a different Boxbox. As data needs to be stored in Jira projects, make sure that ensure your project settings are the same as the source project.Image Removed

...

Inline task

...

create

You can add new tasks directly using the task list, and they will . New tasks appear on the selected level in the hierarchy.

Info

Only Jira issues can be added using the inline task adding.

Image Removed

...

Inline new sub-task adding

You can add sub-tasks directly under a task that has children. New sub-tasks appear on the selected level in the hierarchy.

...

Include existing tasks from a task source

You can add existing tasks to a Box by adjusting its /wiki/spaces/BIGGANTT/pages/315885158 Items scope definition. For example, items that already exist in tools such as Jira and Trello can be included in your Boxbox.

Go to: Add task > Manage scope definition to make adjustments. Image Removed

...

Empty box

When a box doesn't contain tasks you see the following splash screen:Image Removed

...


Create manually

This option lets you create new tasks. 

  1. Click on the tile

...

  1. .

Basic task

To create a basic task, select it from the drop-down:Image RemovedImage Removed

...

Jira issue

To create a new task in a Jira project select it from the drop-down:Image RemovedImage Removed

...

Add existing tasks from Jira

This option lets you add existing tasks from a Jira project.

Click on the tile:
Image Removed

Scope definition settings appear in a pop-up:
To access advanced settings, click the Advanced options link at the bottom:

Portfolio boxes (none scope boxes)

  • You can’t add tasks to portfolio boxes (none scope boxes). The +Add task and inline create features are disabled.

Info

To add new tasks, go to the sub-box of the portfolio box.

To add new tasks:

  1. Go to the sub-box where you want to add new tasks. To find it faster, add the Sub-box column to the view.

  2. Add tasks at the sub-box level.

  3. Return to the portfolio box to see the updated view.

...