  1. Add a post-function to the intended transition, to create a sub-task.
    To add a post-function, navigate to Cogwheel > Issues > Workflows > select the workflow of the project and edit the same.
  2. Select Create Update Issues post function as shown below:
  3. Select the Detailed Fields and add %parent_key% for Issues to update and respective issue type under Issue type section:

    The reason for adding %parent_key% is, it updates the parent issue of the subtask once the post-function executes.
  4. Select the dropdown as Parent issue's due date under Due date and set the desired Due date offset value. You can use "work" to exclude non-working days from the calculation. For example, "5 work", adjusts the date by 5 working days.
  5. Click Update to save the settings. Verify the condition:
  6. Publish the workflow draft.
  7. Perform In Progress transition. Once the transition happens, the Due date of the parent issue gets updated with an offset of 5 working days as per the post-function.
    Image RemovedImage Added
    Image RemovedImage Added


Info

It is recommended to try the provided solution in a non-production environment and ensure everything is working as expected, before trying in a production environment.

...