This article explains how to create sub-tasks based on the components selected and assign them to the respective component leads by using Create on Transition app.

Instructions

Consider a Component with values, Jira and Confluence with users test and user1 as component leads for the components respectively in the respective project.

  1. Add a post-function to the intended transition to create a sub-task.
    To add post-function, navigate to Cogwheel > Issues > Workflows > select the workflow of the project and edit.
  2. Select Create Sub-task post function as shown below.
    Image Modified
  3. Select the Detailed Fields tab and select the Assignee field as %function_componentLead(%original_project%, %entry%)%. By giving the mentioned value in the Assignee field, it will assign the sub-tasks to the respective component leads. 
  4. Select the Conditions & Configuration tab and add %original_components% to Create multiple issues field, so that subtasks will be created depending on the number of components selected.
  5. Click Update to save the settings. Verify the condition.
    Image Modified

  6. Publish the workflow draft.
  7. Perform the transition Awaiting implementation as shown and issues are created based on the condition and will get assigned with respective component leads.
    Image Modified

Note

It is recommended to try the solution provided in a non-production environment and ensure everything is working as expected, before trying in a production environment.

...