On this screen, you can add/remove boards from a box scope. In the Advanced configuration, you can decide if you want your boards and groups to be visualized on the Gantt timeline as tasks.
...
Steps:
Use the Configure Scope button in the message to access scope configuration OR
Go to a box (click on its name)
From the module switcher, select Configuration
on the left go to Tasks > Scope definition
...
Use the Configure Scope button in the message to access scope configuration OR
In Box Configuration, go to Tasks > Task structure
Baselines
To assess the performance of your project over time, you can set Baselines and track deviations from your initial schedule.
Configure the field mapping
Field mapping lets BigPicture know where data can be found in board columns, regardless of the column name. This lets you work with all items in a single BigPicture box, even if your monday boards don't have an identical column setup.
...