The critical path represents the longest sequence of tasks that determines the project duration. The feature highlights tasks on the critical path with the red color.

Tasks on the Critical critical path are also listed in the Gantt module Infobar.

The critical path is based on strong dependencies between tasks (soft dependencies do NOT affect it).
Once you establish task dependencies, the App automatically highlights the Critical critical path (to display it, click on View > Critical Pathpath).

...

Excerpt
namecritical-path-task-dates

Critical path tasks must have start/end dates. Tasks without dates can’t be visualized on the timeline and aren’t included in the critical path.

When one tasks on a critical path doesn’t have start/end dates, the entire critical path is disrupted. Once the start/end dates are provided the critical path will be calculated normally and include all the connected tasks.

...

Tasks that are a part of the critical path are listed in the Infobar > Critical Path path tab.

...

Dependency lag time and ASAP mode

...