Introduction

Basic tasks are tasks stored by BigPicture and are NOT synchronized with monday. Basic tasks can be viewed in:

...

Basic tasks can coexist with other tasks and work great as placeholders or temporary tasks and simulate higher levels in the hierarchy or serve as additional information boxes.

...

Scheduling

Basic tasks follow the same set of rules including linking, sorting, etc. However, dependencies between basic tasks and monday items are NOT synchronized to monday boards, they exist only in BigPicture.

Basic tasks have most of the features of monday items. It is possible to aggregate the MIN (earliest) or MAX (latest) date from all the children’s tasks by editing the column views, converting add aggregations in the column header or column view configuration, convert basic tasks to milestones , and setting create baselines just like with other tasks.

Common use cases

Basic tasks are NOT stored in monday. Exemplary uses of basic tasks:

  • Convert Use basic tasks to milestonesConvert create a custom hierarchy and aggregate data

  • Use basic tasks to monday itemsadd project information, which is not necessary on monday board, e.g. headlines of project phases on a timeline

  • Use basic tasks as placeholdersUse

  • Convert basic tasks as additional notesUse to milestones

  • Convert basic tasks to create a custom hierarchy and aggregate datamonday items

Create basic tasks

Multiexcerpt macro
hiddenfalse
nameCreate-basic-task
fallbackfalse

To create a basic task in a box:

  1. Click the Add task menu icon.Select > Create task > Basic task.

  2. You can also add a basic task directly on the task tree using the “plus” icon.

  3. Fill in the task information.

  4. To create a milestone, activate the Create as a milestone toggle switch. Only one date input will be available, because a milestone is a point in time and cannot have a duration of several days.

  5. To expand another keep task creation boxmodal open after creating the current task, check the Create another option.

  6. Click Create to confirm.

Convert a basic task into a monday item

To convert a basic task into a monday item:

  1. Go to the Gantt module.

  2. Right-click on the basic task.

  3. Select the Convert to monday item option.

  4. Select a projectboard and group to which the task will be added.

  5. Click Create Convert to confirm.

...

Task structure based on basic tasks

Building the task structure with the basic task can be done manually using drag-and-drop, indent, or outdent arrows.

Show all basic tasks in results

To see all basic tasks even when filters are active, use the Show all Basic tasks in results option. The option applies to all filtering methods.

To keep basic tasks visible even when filters are active:

  1. Expand the Filter options menu.

  2. Check the Show all Basic tasks in results option.

...

Limitations

...

Limitations

  • Basic task are not visible on monday boards.