- Jira Agile is installed
- The Story Points field is available
- If you want to build a report using time metric, make sure that time tracking is enabled
- Release Prediction Chart is added to your dashboard
- You have configured the Release Prediction Chart
Reading data on the chart
...
Stats | Description |
---|---|
Projected sprints till release | The number of sprints that should be completed until release date in order to deliver the estimated work |
Story Points / Work time to deliver till release | The work committed to be delivered until release |
Projected release date | The estimated date of release |
Optimistic release date | The estimated date of release, if the team is ahead of schedule with the selected deviation percentage |
Pessimistic release date | The estimated date of release, if the team is behind schedule with the selected deviation percentage |
Sprints tab
The Sprints tab contains details of the closed sprints, open sprints (current sprints) and planned sprints that are included in the report. The sprints are clickable to make the navigation faster for you. For the unplanned sprints the link displays the backlog issues.
...
You can save the chart image, and to do that – right click on the chart area and select Save image.
You can also export the statistics and the sprints details into the XLS file by clicking the Export button.
...
- You have at least 2 completed sprints on the SCRUM board
- You check the Warnings tab from time to time and triage tickets from there. The tickets shown in the Warnings tab are not included into the chart calculations, and thus in order to see the accurate picture on the chart, you might want to triage those tickets first.