Ensure that you are good on the following prerequisites:

Reading data on the chart

Your Release Prediction Chart displays the following information:

  • Sprint related data
    • sprint estimates - The estimated progression of the project
    • sprint actuals - The actual progression of the project
    • planned sprint - The planned progression of the sprints  this line shows how work on the future planned sprints is going to be delivered based on the team's velocity and estimates for the tickets. This line is useful to sanity check your planned sprints as it helps you compare where you want to be at a certain date in the future (sprint estimates line in the future) and how the planned tickets are about to be delivered in the future. For example, you plan to finish sprint 23 on October 18, have all your tickets estimated and added to the sprint, and this workload might be more than a team can deliver within a sprint. Jira will not tell you that you won't deliver your work on time. But you can look at the planned sprint value on the chart and see that delivering tickets estimated for sprint 23 is actually going to happen not earlier than October 27 (see two screenshots below). This is a powerful insight to have both for project planning and for expectation setting.
      Image Added Image Added
    • future normal sprint - The predicted ideal progression of the sprints (or how the sprints should ideally be planned )based on how they have been delivered up till now
  • Version related data
    • version estimated estimates - The estimated progression of the version
    • version actuals - The actuals actual progression of the version
    • planned version - The planned progression of the version (how the version should be planned)
  • Acceptable deviation and danger zone – a user defined deviation area around the future sprint estimates. If the future sprint actuals are inside this area, the team progress is considered to be on track even if the actuals are below the estimates. 
    • Deviation (ahead) – a gold to aim for. This is the hardest line to reach on the chart but at the same time the sweetest one. Very rarely do teams reach that gold but it's worth trying! (smile)
    • Deviation (behind) – this line marks the maximum deviation from planned work beyond which the team progress is not considered to be on track and thus - entering the danger zone.
    • Danger zone – transparent red area below the Deviation (behind) line. Whenever the sprint actuals are inside the danger zone, it means that the team's progress is far below the plan, even below the acceptable deviation. This is a serious point where you would want to sit with your team and identify a reason for this – maybe a team was distracted by work that is not planned for, maybe the plans are too ambitious for the team to deliver, and so on.

The following example shows that the for several sprints the team was bad slow in delivering sprint work and releasing versions for several sprints (sprints – sprints actuals are far below sprints estimates). The team is currently far behind schedule. In order to deliver the estimated work (403 SP) and get back to normal velocity, the team should plan 17 sprints until the projected release date(5/24/2018). Considering the deviation norm, if the team will be is behind schedule, the pessimistic release date should be 9/08/2018. OtherwiseIn an optimistic scenario, if the team will burn burns up more points per sprint and will be than they used to and is ahead of schedule, the optimistic release date should be 2/5/2018. The team progress will be on track as long as the team will be within the deviation norm.

Image RemovedImage Added

Selecting data to display on the chart

The interface chart enables you to customize your report view by showing and hiding the data depending on your current focus. For instance, if you are focused on how you should planned plan the sprints until release and you are not interested in the versions, you can hide the lines by clicking them in the chart legend as shown below. To display the lines again, click them again.

Image RemovedImage Added

Tooltips

For you to have an instant insight into what the certain parts of the chart mean and how much work was delivered at a certain point in time, just hover over a place on the chart. You'll see the summary in the tooltip.

Image RemovedImage Added

Zoom feature

For a better drill down deep dive and work analysis, you can zoom in to see an area representing a short period of time. To zoom in, hover over the chart and use the mouse wheel . Also, you can or your track pad. You can also pan over the chart by clicking and dragging on a section of the chart. To zoom out, you can use your mouse wheel or click the Refresh button.

Image RemovedImage Added

Release Prediciton Chart details in tabs

In addition to chart visualization . For this purpose we provide detailed information, insights, and warnings in a table view below the chart.

...

In addition to sprint information that you would typically find in JIRA, you can also see stats on your team's progress:

Image RemovedImage Added


StatsDescription
Projected sprints till releaseThe number of sprints that should be completed until release date in order to deliver the estimated work
Story Points /
Work time to deliver till release
The work committed to be delivered until release.
Projected release dateThe estimated date of release.
Optimistic release dateThe estimated date of release, if the team is ahead of schedule with the selected deviation percentage.
Pessimistic release dateThe estimated date of release, if the team is behind schedule with the selected deviation percentage.


Sprints tab

The Sprints tab contains details of the closed sprints, open sprints (current sprints) and planned sprints that are included in the report. The sprints are clickable to make the navigation faster for you. For the unplanned sprints the link displays the backlog issues.

Image RemovedImage Added

Versions tab

The Versions tab contains details of on the released and unrealeased versions that are included in the report. For each version you can see the estimates, actuals, start date, end date and prediction date which shows , and the forecasted date showing the projected date of release for the version.

Image RemovedImage Added

Warnings tab

Warnings help you quickly identify tickets that require attention.

We generate warnings when an issue is not estimated and thus might affect the chart's accuracy or when a ticket is resolved outside of the sprint and is not marked as a duplicate or clone. Such tickets are not included into the chart calculations, therefore to ensure the chart's accuracy, you might want to triage such tickets first.

Also, we We also generate warnings for the sprints and versions that will not be are at risk of not being delivered on time.

Image RemovedImage Added

Exporting the Release Prediction Chart data

You can save the chart image, all you have and to do is right that – right click on the chart area and select Save image.
You can also export the statistics and the sprints details into the XLS file by clicking the Export button.

...