You can also switch to the 'Teams' view and assign a team comprising of multiple members who will work on that task. For example, the Team Smartwatch has four members and has a 32h/d capacity, which means that we can reduce duration of the task to three days and still be left with some remaining capacity:

...

Warnings 

Warnings can help you in resolving the most common problems. To enable Warnings go to View > Warnings.  If a task does not have an Original Estimate available, a red line contours the Task (if Warnings are enabled). Click on the task to show the warning in the task detail dialog:

...