Imagine you are a Manager and your team was assigned a creative project. You have prepared a Creative Document containing details of the project and have uploaded this in a Jira issue.
...
On the left side menu, go to project settings and choose the option Workflows. Then on the right-hand side, click the edit Edit button to edit your workflow.
In Text view, select the “in progress” transition.
Select the Post Functions tab, then click Add Post Function.
Select the "Copy/Move attachments"(JSU) post function then click Add.
- Configure the post function:
- Choose the Parent/Sub-task relation since you want the post-function to perform when the parent issue is transitioned and for the attachments to be copied on the sub-tasks.
- Select the "always copy attachments" option from the drop-down menu of the configuration to have all the attachments you will add during the transition on the transition screen copied through to the sub-tasks.In this drop-down, you have the option to select a field of your parent issue to have a value, in order for the attachments to be copied to the sub-tasks. By configuring this, the attachments added on the transition screen will only be copied to the sub-tasks if that field has a value.
- Follow the same steps if you want the attachments that existed in your parent issue before the transition started to be copied through too.
- Click Add at the bottom of the page.
- Publish your workflow.
...