Introduction
You can enable the ASAP mode for strong dependencies - . In such case, the scheduling mechanism will try to reduce the gap between dependent tasks to a minimum. When you set this toggle- switch to active, the App app remembers the settings, and all future dependencies are dependencies will be created in with the ASAP mode.
Info |
---|
The Source task date rules the Target task date. It's a uni-directional relationship. |
...
In other words, dependency in ASAP mode always schedules the target task as soon as possible based on dependency type. There are no restrictions on how many dependencies are created for each source or target task as long as they are not creating circular relationshiprelationships. If a task is moved to a prohibited position (based on dependency type and mode), it is moved back/forward to the appropriate position.
...
ASAP mode on
With ASAP mode "on", there is only one position in which where a task dependency can be placed by place a dependencytask. The lag time is respected. With ASAP mode "on", the date of the target task should be the same as the date of the source task.
...