Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Contents:

Table of Contents

...

Dependency path calculation

Use strong dependenciesto determine the correct order of tasks

  • The path is calculated from the end (the last task(s) in the project)

  • The algorithm works backward, looking for strong links connecting tasks

  • The most direct path (without a time gap between tasks) is highlighted

  • A gap between tasks is allowed only if an ASAP link has "lag time" added

...

Non-working days

The non-working days do not affect the critical path calculation. This means that if there are two tasks with a dependency on the critical path and the predecessor ends before a non-working day, the App will move the successor to start on the first working day, and both will remain on the critical path:

...

Critical Path Tab

Tasks that are a part of the critical path are listed in the Infobar > Critical Path tab.

...