Versions Compared
Key
- This line was added.
- This line was removed.
- Formatting was changed.
Scenario
"Our Jira project is a time-boxed initiative, and we'd like to track overall completion progress in terms of hours spent vs estimated"
We'll show you how to do all of this using Power Scripts™ for Jira - a powerful scripting tool to help automate your Jira.
What This Script Does
Whenever an issue within the project is created, edited, or a worklog is generated, this script runs.
It sums all the estimated hours on all issues in the project, sums all the logged work hours on all issues in the project, calculates the project percentage complete (in terms of hours), and then adds a human-readable comment to a "master tracker" issue with the latest data.
e.g. "This project has *200h* estimated work with *120h* spent for a total of *80h* remaining. It is *60%* complete."
It can easily be modified to populate custom fields instead of generating a comment. This has now been reflected in the example script.
Prerequisites
You have Jira Core, Software, or Service Desk installed
You have Power Scripts™ for Jira installed
You have created four custom fields of type "interval" and mapped those custom field IDs to the following aliases in the sil.aliases file:
projectTotalTimeEstimated
projectTotalWorkLogged
projectTotalTimeRemaining
projectPercentComplete
Modifications Required
Modify the script to reference a single project to calculate totals
Modify the script to reference a single issue to append comments to
Configuration
Trigger this script on the following system events:
Issue Created
Issue Edited
Work Logged on Issue
Table of Contents
Table of Contents |
---|
Script
Script
This script will run whenever an issue is created, updated, or work is logged on an issues in the applicable project.
It adds a comment to a specific issue to explain, in human readable terms, how many total hours are esimated and logged in the project, and gives a percentage complete value. One could mod the script to populate fields instead of adding a comment.
Code Block |
---|
string projectInScope="SMSW"; // the project you want to sum up
string masterIssue="SMSW-23"; // issue where you want to capture this info
if(project==projectInScope) { // if invoked via listener, limit the scope
string jql="project="+projectInScope;
string [] allProjectIssues=selectIssues(jql);
string issue;
string commentText;
interval sumOriginalEstimate;
interval sumTimeSpent;
interval sumTimeRemaining;
number hoursOriginalEstimate;
number hoursTimeSpent;
number completePercent;
number countIssues=0;
for(issue in allProjectIssues) {
sumOriginalEstimate += %issue%.originalEstimate;
sumTimeSpent += %issue%.timeSpent;
countIssues +=1;
}
sumTimeRemaining = sumOriginalEstimate - sumTimeSpent;
hoursTimeSpent = sumTimeSpent;
hoursOriginalEstimate = sumOriginalEstimate;
completePercent = round((hoursTimeSpent/hoursOriginalEstimate)*100,0);
%masterIssue%.projectTotalTimeEstimated = sumOriginalEstimate;
%masterIssue%.projectTotalWorkLogged = sumTimeSpent;
%masterIssue%.projectTotalTimeRemaining = sumTimeRemaining;
%masterIssue%.projectPercentComplete = completePercent;
string commentTextA = "This project has *"+sumOriginalEstimate+"* estimated work";
string commentTextB = " with *"+sumTimeSpent+"* spent for a total of *";
string commentTextC = ""+sumTimeRemaining+"* remaining. ";
string commentTextD = "It is *"+completePercent+"%* complete. ";
string commentTextE = "This update brought to you changes made in "+key+".";
commentText = commentTextA + commentTextB + commentTextC + commentTextD + commentTextE;
addComment(masterIssue, currentUser(), commentText);
} |
Table of Contents
Table of Contents |
---|